Silver Lake acquired the Lakewood Gold Processing Facility located 5 km southeast of Kalgoorlie and 45 km from the Daisy Milano mine in December 2007.

FIGURE 1FIGURE 1
Lakewood Gold Processing FacilityClick image to enlarge

Modifications to the existing circuit to optimize processing of the high grade ore from Daisy Milano were completed in April 2008 including a major refurbishment programme.

In February 2010 the facility was upgraded from 300,000tpa to 600,000 tpa for a low capital cost of $4.0 million.  The facility is now capable of processing 400,000 tpa of hardrock or up to 600,000 tpa of blended rock.

Upgraded Lakewood Mill