Silver Lake acquired the Lakewood Gold Processing Facility located 5 km southeast of Kalgoorlie and 45 km from the Daisy Milano mine in December 2007.
Modifications to the existing circuit to optimize processing of the high grade ore from Daisy Milano were completed in April 2008 including a major refurbishment programme.
In February 2010 the facility was upgraded from 300,000tpa to 600,000 tpa for a low capital cost of $4.0 million. The facility is now capable of processing 400,000 tpa of hardrock or up to 600,000 tpa of blended rock.